Prior to installing any UST system, from which authority must the owner/operator obtain the required permit?

Prepare for the A-B Operator Petro-Tech Exam. Utilize our flashcards and multiple choice questions, each complete with hints and explanations. Ensure your success on the test!

Multiple Choice

Prior to installing any UST system, from which authority must the owner/operator obtain the required permit?

Explanation:
Before you install an underground storage tank, the permit to begin work comes from the local building official. This authority reviews the project for compliance with local building codes, zoning, site layout, and safety requirements, and grants formal approval to start construction. Other agencies, such as the state fire marshal or DEQ, may require separate environmental or fire-safety permits, but the initial authorization to install typically originates with the local building department. The city council does not issue installation permits.

Before you install an underground storage tank, the permit to begin work comes from the local building official. This authority reviews the project for compliance with local building codes, zoning, site layout, and safety requirements, and grants formal approval to start construction. Other agencies, such as the state fire marshal or DEQ, may require separate environmental or fire-safety permits, but the initial authorization to install typically originates with the local building department. The city council does not issue installation permits.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy